How Long Will It Take to Deliver My Process Module?
A typical project timeline for a $100,000 to $1,000,000 project is illustrated below. Part of the value add of any well-run, mid-sized company is the ability to execute quickly.
• Authority and responsibility are delegated downward to the greatest extent possible, empowering our project team members to make quick decisions.• Projects are excuted efficiently because communication is optimized. Our team members routinely wear more than one hat (e.g. the Project Manager may also be the Process Design Engineer on a given project), resulting in less confusion and delays.
Schedule improvements will result from the following:
• Prompt receipt of your purchase order• Reasonable and pragmatic documentation requirements• Prompt review and approval by the client at indicated milestone points• Shorter critical path equipment lead times than are shown in this illustration• Equipment expediting premiums (not an option with some equipment manufacturers)• Shop labor overtime premiums